Report an Activity
In this topic, we'll show you how to report an activity.
- Click on the Schedule module from the left navigation.
- Click on Published Project Plan from the drop-down list.
- Right click on the activity, that you want to report.
- Click on the Report from the actions menu.
- Enter the percentage complete in the Percentage Complete input box.
- Click on the Date field and select a data from the calendar.
- Enter the man-hours in the Manhours input box.
- Enter the completed quantity in the Completed Quantity input box.
- Click on the Attach file(s) icon.
- Click on the Attach a file button. Select a file(s) from your computer and attach it.
- Click on the Done button.
- Click on the Submit button.
- Click on the OK button. The Activity will be reported successfully.