Re-Schedule Activities
In this topic, we'll show you how to re-schedule activities in the Master Project Plan.
- Click on the Schedule module from the left navigation.
- Click on Master Project Plan from the drop-down list.
- Right click on the activity, that you want to re-schedule from the Master Project Plan.
- Click on the Re-Schedule from the action list.
- Click on the Start Date and Finish Date fields and change start and finish dates from the calendar.
- Click on the Save button.
- Click on the OK button.
Please note that all resource reservations such as Equipment Reservation, Crew Reservation etc. will be dropped when you reschedule the activity. - The activity will be successfully re-scheduled.