Skip to content

Re-Schedule Activities

 In this topic, we'll show you how to re-schedule activities in the Master Project Plan.

  1. Click on the Schedule module from the left navigation.



  2. Click on Master Project Plan from the drop-down list.



  3.  Right click on the activity, that you want to re-schedule from the Master Project Plan.   



  4. Click on the Re-Schedule from the action list.



  5. Click on the Start Date and Finish Date fields and change start and finish dates from the calendar.



  6. Click on the Save button.



  7. Click on the OK button.
    Please note that all resource reservations such as Equipment Reservation, Crew Reservation etc. will be dropped when you reschedule the activity.



  8. The activity will be successfully re-scheduled.