Activity Status and their Definitions

Sr. No.

Activity Status

Definition

01

Get Ready

Activities that are scheduled within the next one week, will have this status

02

Future Activity

Activities, that are scheduled beyond next one week, will have this status

03

Proceed

Activities which planned to be executed today, will have this status

04

In Progress

Activities that have been committed and started, will have this status

05

Completed and Awaiting Approval

Activities that are reported, will have this status

06

Completed and Approved

Activities that are completed and approved, will have this status

07

Work Complete, Checked and Rejected

Activities that are marked complete but were rejected by the Inspector, will have this status

08

Past Due Activity

Activities that were planned for the past week or earlier but didn’t complete, will have this status

09

Activity Stopped

Activities that are stopped, will have this status

10

Frozen

Past due activities that were either in progress or were stopped, but were not reported complete, will have this status

11

Canceled

Activities that were canceled, will have this status