Activity Status and their Definitions
Sr. No. |
Activity Status |
Definition |
01 |
Get Ready |
Activities that are scheduled within the next one week, will have this status |
02 |
Future Activity |
Activities, that are scheduled beyond next one week, will have this status |
03 |
Proceed |
Activities which planned to be executed today, will have this status |
04 |
In Progress |
Activities that have been committed and started, will have this status |
05 |
Completed and Awaiting Approval |
Activities that are reported, will have this status |
06 |
Completed and Approved |
Activities that are completed and approved, will have this status |
07 |
Work Complete, Checked and Rejected |
Activities that are marked complete but were rejected by the Inspector, will have this status |
08 |
Past Due Activity |
Activities that were planned for the past week or earlier but didn’t complete, will have this status |
09 |
Activity Stopped |
Activities that are stopped, will have this status |
10 |
Frozen |
Past due activities that were either in progress or were stopped, but were not reported complete, will have this status |
11 |
Canceled |
Activities that were canceled, will have this status |